Dry docking and installing WBTS

dry docking:
Lady Isabel 5th special survey,  
Lady Irina 5th special, 
Lady Nora 4th special survey
Location Alkor Safe syipyard Gdansk Poland

steel renewal,
ballast and bilge line renewal,
complete overhauling of folding type Roden staal hatches
main engine repairs and commissioning 
several pumps and E-motor overhauling
hull treatment such as, cleaning / blasting / and painting (Jotun system)
Classification Lloyds special survey handling 

Installing Headway WBTS delivery by Headway and Reikon
Engineering by Goltens Leek
Electrical installation by Eekels

project time frame 10 August till 15 October 

Project information

  • Project date 2021-08-10
  • Project published 2021-10-29